ufh prep

Discussion in 'Subfloor Preparation' started by oddbod_jnr, Jan 26, 2016.

  1. oddbod_jnr

    oddbod_jnr Well-Known Member

    649
    242
    43
    hi lads I'm getting conflicting advice from fballs and a few others so I will ask you.
    New concrete base so needs dpm
    customer wants ufh matting under camero so what's best prep .
    balls said 1200 then dpm then 300
    but isn't 1200 a lower compression than 300 . also doesn't it need a fibre screed for ufh.
     
  2. jamief

    jamief Well-Known Member

    72
    24
    8
    Cant you dpm prime then 700?
     
  3. merit

    merit Well-Known Member

    8,220
    1,679
    113
    Sod that...leave it to dry, 10mm of 1200 or 300. Leave for a few days then fit
     