Correct and best Prep required for half timber floorboards , half asphalt floor with ceramics ?

Discussion in 'Subfloor Preparation' started by TONY74, Dec 4, 2017.

  1. TONY74

    TONY74 Well-Known Member

    75
    3
    8
    Hello lads as the title says got a job to look at the sub floor is half floorboards and half asphalt with some well stuck ceramics on top. I was thinking 6/ 9mm ply on top of the floor boards nailed down with ring shanks at 6 inch centres . Prime full area with p51 or similar then ardex na all over . The finish will be camaro . Cheers ?
     
  2. merit

    merit Well-Known Member

    8,220
    1,679
    113
    Sounds good to me


    Sent from my iPhone using Tapatalk
     
  3. Rugmunching

    Rugmunching Well-Known Member

    3,871
    677
    113
    Good to go!
     
  4. Spacey

    Spacey Super Moderator Staff Member

    6,503
    1,881
    113
    Shouldn’t really go deeper than 6mm over ashpalt.
    So 6mm ply over floorboards nailed every 4 inches.
    3mm coat of NA no primer
    Ardex 1c DPM
    Another 3mm coat of NA
    Full feather over the lot
     
  5. TONY74

    TONY74 Well-Known Member

    75
    3
    8
    Ardex dpm over ply ?
     
  6. Spacey

    Spacey Super Moderator Staff Member

    6,503
    1,881
    113
    No over NA on asphalt o_O
     
  7. TONY74

    TONY74 Well-Known Member

    75
    3
    8
    Didnt know you had to dpm over asphalt mate ?
     
  8. Spacey

    Spacey Super Moderator Staff Member

    6,503
    1,881
    113
    Asphalt is also the dpm and tends to be found in older properties direct to earth and is normally damaged or cracked so it’s best to use a liquid Dpm to be safe
     
  9. TONY74

    TONY74 Well-Known Member

    75
    3
    8
    OK cheers mate . What about on quarries ? Dpm then na ? Im rusty as you can prob tell . I need to go on a refresher course i think .
     
  10. Spacey

    Spacey Super Moderator Staff Member

    6,503
    1,881
    113
    Degrees NA dpm NA
     